CS 26.331 Compliance plan for STC holders
Compliance
with point 26.331 of Part-26 is demonstrated when a compliance
plan exists that includes:
(a) a project schedule identifying all the major milestones for meeting the compliance times specified in points 26.332 to 26.334 of Part-26;
(b) an explanation of how the changes that affect the FCS will be identified and presented;
(c) a proposed means of compliance with the DTE required by points 26.333 and 26.334 of Part-26;
(d) a plan for
submitting drafts of all the compliance items required by point 26.330 of Part-26 for review by EASA not less than 60 days before the
applicable compliance date.
[Issue:
26/3]