GM1 21.A.126(b)(5) Production inspection system — Engineering and manufacturing review procedure

ED Decision 2022/021/R

(a) The procedure should permit to record the deviation, to present it to the design approval holder (DAH) under the provisions of point 21.A.122, and to record the results of the review and action taken consequently as regards the part/product.

(b) Any unintentional deviation from the manufacturing/inspection data should be recorded and handled in accordance with Part 21, Section A, Subpart D or E as changes to the approved design.