AMC1 ADR.OPS.B.100(b)(5) Suspension of runway operations and runway closure

ED Decision 2024/004/R

ACTIONS BEFORE RECOMMENCEMENT OF RUNWAY OPERATIONS

The following actions should be completed if runway operations are recommenced following a suspension or closure of runway operations:

(a) remedial works are completed, e.g. clearance of FOD, wildlife remains, runway lighting repair, removal of disabled aircraft;

(b) all vehicles and personnel have vacated the runway and report to the air traffic services;

(c) a runway inspection under the authorisation of air traffic services is conducted;

(d) runway availability is confirmed to air traffic services;

(e) relevant NOTAM, if published, is cancelled;

(f) runway availability is promulgated by air traffic services using ATIS and radiotelephony.