ED Decision 2024/004/R
ACTIONS BEFORE RECOMMENCEMENT OF RUNWAY OPERATIONS
The following actions should be completed if runway operations are recommenced following a suspension or closure of runway operations:
(a) remedial works are completed, e.g. clearance of FOD, wildlife remains, runway lighting repair, removal of disabled aircraft;
(b) all vehicles and personnel have vacated the runway and report to the air traffic services;
(c) a runway inspection under the authorisation of air traffic services is conducted;
(d) runway availability is confirmed to air traffic services;
(e) relevant NOTAM, if published, is cancelled;
(f) runway availability is promulgated by air traffic services using ATIS and radiotelephony.