AMC1 ADR.OPS.B.035(a) Operations in winter conditions

ED Decision 2021/003/R

AERODROME SNOW PLAN

The aerodrome snow plan should reflect the exposure of the aerodrome to winter conditions and should include the following:

(a) the Snow Committee members and the person in charge of the winter operation, with a chain of command giving a breakdown in duties;

(b) methods of communication between aerodrome operations, air traffic services, and the MET provider;

(c) the equipment available for snow clearance and surface treatment. This should include equipment for ploughing, sweeping, and blowing snow and application of materials;

(d) priority of surfaces to be cleared, and clearance limits for aircraft using the aerodrome;

(e) collection of information for RCR and dissemination of this information;

(f) designated snow dumping or melting areas;

(g) an alerting system in order that sufficient warning is given to all bodies concerned;

(h) the manpower available, including staff for equipment maintenance arrangements for shifts, and call-out procedures;

(i) deployment of equipment and tactical approaches to be used;

(j) general principles to be followed in deciding when to close runways for snow clearance and designation of management personnel authorised to take the decision;

(k) methods of assessing and reporting the surface conditions; and

(l) criteria for the suspension of runway operations.