AMC2 ADR.OPS.B.070 Aerodrome works safety

ED Decision 2024/004/R

RUNWAY PAVEMENT OVERLAYS

The aerodrome operator should ensure that:

(a)     when a runway is to be returned temporarily to an operational status before resurfacing is complete, the longitudinal slope of the temporary ramp, measured with reference to the existing runway surface or previous overlay course, should be:

(1)     0.5 to 1.0 %for overlays up to and including 5 cm in thickness; and

(2)     not more than 0.5 % for overlays more than 5 cm in thickness.

(b)     Runway overlaying proceeds from one end of the runway towards the other end so that based on runway utilisation, most aircraft operations will experience a down ramp.

(c)      The entire width of the runway is overlaid during each work session.

(d)     Before a runway being overlaid is returned to a temporary operational status, a runway centre line marking, conforming to the applicable specifications included in the aerodrome certification basis of the aerodrome, should be provided.

(e)     The location of any temporary threshold should be identified by a 3.6 m wide transverse stripe.

[applicable until 23 May 2025 – ED Decision 2021/003/R]