Appendix
3 to AMC 20-29 – Change of Composite Material and/or Process
ED Decision 2010/003/R
1. It is necessary to re-certify
composite structures, which during production, incorporate substitutions of,
or changes to, the materials and/or processes from those originally
substantiated at the time of initial certification. For example, the original
material supplier may either change its product, or cease production.
Manufacturers may also find it necessary to modify their production processes
to improve efficiency or correct product deficiencies. In either case, care
must be taken to ensure that modifications and/or changes are adequately
investigated to ensure the continued adequacy of already certificated
composite structure. This appendix covers such material and/or process
changes, but does not address other changes to design (e.g., geometry,
loading). The definition of the materials and processes used is required in
the specifications by Part 21.A.31. Changes to the material
and process specifications are often major changes in type design and must be
addressed as such under Part-21, subpart D or E as applicable.
2. The qualification and structural
substantiation of new or modified materials and/or processes used to produce
parts of a previously certified aircraft product requires:
a. The identification of the key material
and/or process parameters governing performances;
b. The definition of the appropriate
tests able to measure these parameters; and
c. The definition of pass/fail criteria
for these tests.
3. ‘Qualification’ procedures developed by
every manufacturer include specifications covering:
a. Physical and chemical properties,
b. Mechanical properties (coupon level),
and
c. Reproducibility (by testing several
batches).
4. Specifications and manufacturing
quality procedures are designed to control specific materials and processes to
achieve stable and repeatable structure for that combination of materials and
processes. However, the interchangeability of alternate materials and
processes for a structural application cannot be assumed if one only considers
the properties outlined in those specifications (as it could be for materials
that are much less process dependent, e.g., some metallic material forms). A
structure fabricated using new or modified materials and/or processes, which
meet the ‘qualification’ tests required for the original material and process
specifications, does not necessarily produce components that meet all the
original engineering requirements for the previously certified structure.
5. Until improvements in identifying the
complex relations between key material parameters that govern composite
processing occurs, there will be a need for extensive and diverse testing that
directly interrogates material performance using a range of representative
specimens of increasing complexity in building block tests. Furthermore,
failure modes may vary from one material and/or process to another, and
analytical models are sometimes insufficiently precise to reliably predict
failure without sufficient empirical data. Therefore, a step-by-step test
verification with more complex specimens may be required.
6. Classification of Material or Process Change
Material
and/or process changes require appropriate classification in order to aid the
determination of the extent of investigation necessary. Some minor changes may
only require material equivalency sampling tests to be completed at the base
of the test pyramid, whilst more significant changes will require more
extensive investigations, including possibly a new structural substantiation.
a. Any of the following situations
requires further investigation of possible changes to a given composite
structure:
(1) Case A: A change in one or both of the
basic constituents, resin, or fibre (including sizing or surface treatment
alone) would yield an alternate material. Other changes that result in an
alternate material include changes in fabric weave style, fibre aerial weight
and resin content.
(2) Case B: Same basic constituents, but any
change of the resin impregnation method. Such changes include: (i) prepregging
process (e.g., solvent bath to hot melt coating), (ii) tow size (3k, 6k, 12k)
for tape material forms with the same fibre areal weight, (iii) prepregging
machine at the same suppliers, (iv) supplier change for a same material
(licensed supplier).
(3) Case C: Same material, but modification
of the processing route (if the modification to the processing route governs
eventual composite mechanical properties). Example process changes of
significance include: (i) curing cycle, (ii) bond surface preparation, (iii)
changes in the resin transfer moulding process used in fabricating parts from
dry fibre forms, (iv) tooling, (v) lay-up method, (vi) environmental
parameters of the material lay-up room, and (vii) major assembly procedures.
b. For each of the above cases, a
distinction should be made between those changes intended to be a replica of
the former material/process combination (Case B and some of Case C) and those
which are “truly new material” (Case A and some of Case C). So, two classes
are proposed:
(1) “Identical materials/processes” in cases
intended to create a replica structure.
(2) “Alternative materials/processes” in
cases intended to create truly new structure.
c. Within the “identical
materials/processes” class, a sub-classification can be made between a change
of the prepregging machine alone at the supplier and licensed production
elsewhere. For the time being, a change to a new fibre produced under a
licensed process and reputed to be a replica of the former one, will be dealt
with as an “alternative material/process”.
d. Some minor changes within the class
representing identical materials/processes may not interact with structural
performances (e.g., prepreg release papers, some bagging materials, etc.) and
should not be submitted to the Agency as part of the change. However, the
manufacturers (or the supplier) should develop a proper system for screening
those changes, with adequate proficiency at all relevant decision levels.
Other minor material changes that fall under Case B may warrant sampling tests
to show equivalency only at lower levels of building block substantiation.
e. Case C changes that may yield major
changes in material and structural performance need to be evaluated at all
appropriate levels of the building block tests to determine whether the
manufacturing process change yields identical or alternate materials. Engineering
judgment will be needed in determining the extent of testing based on the
proposed manufacturing change.
f. Case A (alternative material) should
always be considered as an important change, which requires structural
substantiation. It is not recommended to try a sub-classification according to
the basic constituents being changed, as material behaviour (e.g., sensitivity
to stress concentrations) may be governed by interfacial properties, which may
be affected by either a fibre or a resin change.
7. Substantiation Method. Only the technical aspects of substantiation
are addressed below.
a. Compliance Philosophy. Substantiation should be based on a comparability
study between the structural performances of the material accepted for type
certification, and the second material. Whatever the modification proposed for
a certificated item, the revised margins of safety should remain adequate. Any
reduction in the previously demonstrated margin should be investigated in
detail.
(1) Alternative Material/Process: New design values for all
relevant properties should be determined for any alternate material/process
combination. Analytical models initially used to certify structure, including
failure prediction models, should be reviewed and, if necessary, substantiated
by tests. The procurement specification should be modified (or a new
specification suited to the selected material should be defined) to ensure key
quality variations are adequately controlled and new acceptance criteria defined.
For example, changing from first to second generation of carbon fibres may
improve tensile strength properties by more than 20% and a new acceptability
threshold will be needed in the specification of the alternate material to
ensure the detection of quality variations.
(2) Identical Material: Data should be provided that
demonstrates that the original design values (whatever the level of
investigation, material or design) remain valid. Statistical methods need to
be employed for data to ensure that key design properties come from the same
populations as the original material/process combination. Calculation models
including failure prediction should remain the same. The technical content of
the procurement specification (Case B) should not need to be changed to
properly control quality.
b. Testing.
(1) The extent of testing needed to
substantiate a material change should address the inherent structural
behaviour of the composite and will be a function of the airworthiness
significance of the part and the material change definition. For example, the
investigation level might be restricted to the generic specimens at the test
pyramid base (refer to figures in paragraph 7) for an identical material, but
non-generic test articles from higher up the pyramid should be included for an
alternative material. Care needs to be taken to ensure that the test methods
used yield data compatible with data used to determine properties of the
original structure.
(2) The testing that may be required
for a range of possible material and/or process changes should consider all
levels of structural substantiation that may be affected. In some instances
(e.g., a minor cure cycle change), possible consequences can be assessed by
tests on generic specimens only. For other changes, like those involving
tooling (e.g., from a full bag process to thermo-expansive cores), the
assessment should include an evaluation of the component itself (sometimes
called the “tool proof test”). In this case, an expanded NDI procedure should
be required for the first items to be produced. This should be supplemented –
if deemed necessary – by “cut up” specimens from a representative component,
for physical or mechanical investigations.
c. Number of Batches.
(1) The purpose for testing a number of batches
is the demonstration of an acceptable reproducibility of material
characteristics. The number of batches required should take into account:
material classification (identical or alternative), the investigation level
(non-generic or generic specimen) the source of supply, and the property under
investigation. Care should be taken to investigate the variation of both basic
material and the manufacturing process.
(2) Existing references (e.g., The Composite
Materials Handbook (CMH-17) Volumes 1 and 3, FAA Technical Report DOT/
FAA/AR-03/19), addressing composite qualification and equivalence and the
building block approach, provide more detailed guidance regarding batch and
test numbers and the appropriate statistical analysis up to laminate level.
Changes at higher pyramid levels, or those associated with other material
forms, e.g., braided VARTM (Vacuum-Assisted Resin Transfer Moulding)
structure, may require use of other statistical procedures or engineering
methods.
d. Pass/Fail Criteria. Target pass/fail criteria should be established as part of the test
programme. For strength considerations for instance, a statistical analysis of
test data should demonstrate that new design values derived for the second
material provide an adequate margin of safety. Therefore, provision should be
made for a sufficient number of test specimens to allow for such analysis. At
the non-generic level, when only one test article is used to assess a
structural feature, the pass criteria should be a result acceptable with
respect to design ultimate loads. In the cases where test results show lower
margins of safety, certification documentation will need to be revised.
e. Other Considerations. For characteristics other than static
strength (all those listed in AMC
20-29,
paragraphs 8, 9, 10 and 11), the substantiation should also ensure an
equivalent level of safety.
[Amdt 20/6]
Loading collections...