ARA.GEN.305 Oversight programme

EASA aviation authorities must maintain oversight programs for aircrew, training organizations, and FSTD certificate holders. These risk-based programs include audits, inspections, and meetings, with planning cycles up to 48 months (72 for LAPL/PPL training). Effective safety management and continuous reporting can extend these cycles.

Frequently Asked Questions

The competent authority should consider the specific nature of the organization, the complexity of its activities, and the results of past certification and/or oversight activities, basing the program on an assessment of associated risks.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The oversight program must include inspections, including unannounced inspections, as appropriate.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The oversight planning cycle may be extended to a maximum of 72 months if specific conditions are met, including effective hazard identification, continuous control over changes, no level 1 findings, and timely implementation of corrective actions.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The oversight program should include audits and inspections (including ramp and unannounced inspections), and meetings between the accountable manager and the competent authority.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The oversight planning cycle may be extended if the competent authority has established that the organization has demonstrated effective hazard identification and risk management, continuous control over changes, no level 1 findings, and timely implementation of corrective actions during the previous 24 months.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The applicability date of Regulation (EU) 2018/1119 according to ARA.GEN.305 is 2 September, 2018.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

EASA Logo

ARA.GEN.305 Oversight programme

Regulation (EU) 2018/1119

(a)     The competent authority shall establish and maintain an oversight programme covering the oversight activities required by ARA.GEN.300 and by ARO.RAMP.

(b)     For organisations certified by the competent authority and FSTD qualification certificate holders, the oversight programme shall be developedtaking into account the specific nature of the organisation, the complexity of its activities, the results of past certification and/or oversight activities and shall be based on the assessment of associated risks. It shall include within each oversight planning cycle:

(1)     audits and inspections, including ramp and unannounced inspections as appropriate; and

(2)     meetings convened between the accountable manager and the competent authority to ensure both remain informed of significant issues.

(c)      For organisations certified by the competent authority and FSTD qualification certificate holders an oversight planning cycle not exceeding 24 months shall be applied.

The oversight planning cycle may be reduced if there is evidence that the safety performance of the organisation or the FTSD qualification certificate holder has decreased.

The oversight planning cycle may be extended to a maximum of 36 months if the competent authority has established that, during the previous 24 months:

(1)     the organisation has demonstrated an effective identification of aviation safety hazards and management of associated risks;

(2)     the organisation has continuously demonstrated under ORA.GEN.130 that it has full control over all changes;

(3)     no level 1 findings have been issued; and

(4)     all corrective actions have been implemented within the time period accepted or extended by the competent authority as defined in ARA.GEN.350(d)(2).

The oversight planning cycle may be further extended to a maximum of 48 months if, in addition to the above, the organisation has established, and the competent authority has approved, an effective continuous reporting system to the competent authority on the safety performance and regulatory compliance of the organisation itself.

(ca)    Notwithstanding (c), for organisations only providing training towards the LAPL, PPL, SPL or BPL and associated ratings and certificates, an oversight planning cycle not exceeding 48 months shall be applied. The oversight planning cycle shall be reduced if there is evidence that the safety performance of the organisation holder has decreased.

                   The oversight planning cycle may be extended to a maximum of 72 months, if the competent authority has established that, during the previous 48 months:

(1)     the organisation has demonstrated an effective identification of aviation safety hazards and management of associated risks, as demonstrated by the results of the annual review in accordance with ORA.GEN.200(c);

(2)     the organisation has continuously maintained control over all changes in accordance with ORA.GEN.130 as demonstrated by the results of the annual review in accordance with ORA.GEN.200(c);

(3)     no level 1 findings have been issued; and

(4)     all corrective actions have been implemented within the time period accepted or extended by the competent authority as defined in ARA.GEN.350(d)(2).

(d)     For persons holding a licence, certificate, rating, or attestation issued by the competent authority the oversight programme shall include inspections, including unannounced inspections, as appropriate.

(e)     The oversight programme shall include records of the dates when audits, inspections and meetings are due and when such audits, inspections and meetings have been carried out.

(f)      Notwithstanding points (b), (c), and (ca), the oversight programme of DTOs shall be developed taking into account the specific nature of the organisation, the complexity of its activities and the results of past oversight activities and shall be based on the assessment of risks associated with the type of training provided. The oversight activities shall include inspections, including unannounced inspections, and may, as deemed necessary by the competent authority, include audits.

Related

AI for Aviation Professionals

Aviation.Bot is an AI tool that assists you with aviation compliance.