GM6 Article 18(f) Tasks of the competent
authorities
ED Decision 2022/022/R
COORDINATION MECHANISM — SCOPE OF TASKS IN THE CONTEXT OF MULTILEVEL GOVERNANCE
Depending on the phase of the U-space deployment, there are different needs as regards the participation of relevant stakeholders referred to in Article 18(f). These different needs and the engagement of different stakeholders may lead to differentiated coordination mechanism set-ups. The scope of the main tasks to be coordinated during each U-space life cycle phase (Plan—Execute—Review), as shown in Figure 1, in conjunction with key stakeholders (who), the timing of their engagement (when), and the coordination activities required (how), are outlined in Table 1 below (the three areas of coordination required by Article 18(f) are shown for each phase).
Table 1: Overview of the
who–when–how during the different phases of the U-space coordination mechanism
|
|
Who |
When |
How |
Remarks |
|
PLANNING PHASE |
||||
|
U-space designation |
Civil aviation authorities, U-space coordinator, ministries (e.g. environment, culture, interior), the military, ANSPs, regional and local authorities, and other U-space actors (e.g. CIS providers, USSPs, UAS operators). |
At the very beginning of the U-space designation process and after the airspace risk assessment (Article 3(1). |
By consultation, reiteration and alignment among national, regional and local authorities. |
Member States are the final decision-makers on the U‑space designation after collaboration or consultation with relevant stakeholders (e.g. civil aviation and military authorities). |
|
U-space
airspace restrictions |
National authorities by defining geo‑zones (ref. Article 15 of Regulation (EU) 2019/947). Regional or local authorities for the U‑space designation |
During the initial U‑space designation. |
By following the consultation process. Based on the national geo‑zones, additional regional and local restrictions may apply. |
U-space is a geo‑zone. |
|
U-space service
determination |
Key actors: civil aviation authorities Supporting actors: ANSPs, USSPs, UAS operator associations, regional and local authorities, etc. |
As part of the U-space designation process. |
Coordination only for the optional services through the consultation process. |
Mandatory and optional U-space services should not be confused with commercial or publicly offered UAS services. |
|
EXECUTION PHASE |
||||
|
U-space designation |
ATSPs (when available), USSPs, U‑space coordinator and any other relevant regional/local stakeholders (e.g. emergency medical services, etc.). |
Monitored throughout the operations. |
Monitored in collecting safety and operational indicators: safety events (accidents, AIRPROX, etc.), occurrences of dynamic configurations, conformance monitoring, rogue drones or rogue UAS operators, etc. |
— |
|
U-space
airspace restrictions |
The authorised actors provide real‑time U-space restrictions as part of the CIS. For example, a local authority (e.g. municipal police, fire brigade) and the USSP/ANSP in alignment with the national authorities’ policies. |
When an emergency is identified and verified by local authorities. ANSPs or USSPs will be notified, and the information will be automatically transferred to the UAS operator. |
Automated/real-time triggering of U-space restrictions prompted from verified emergencies by local authorities. Information flow and decision‑making to be managed and governed by U‑space standard operations. |
These U-space restrictions refer to exceptional cases that result in temporary and/or of a more pseudo‑permanent nature. Accident reporting mechanisms may link to this task. |
|
U-space service
determination |
n/a |
n/a |
n/a |
Various predetermined and
agreed U-space services will be used during a mission. |
|
REVIEW PHASE |
||||
|
U-space designation |
Civil aviation authorities, U-space coordinator, ANSPs and/or CIS providers, USSPs, ‘hearing’ authority / regional/local actors / authorities, UAS operator associations |
As part of regular U-space review exercises. After mitigation of exceptional cases. |
Through consideration of U‑space KPIs’ monitoring and feedback from stakeholders. Through
risk assessment, airspace restrictions, |
Follow-up |
|
U-space
airspace restrictions |
Follow-up |
|||
|
U-space service
determination |
Evaluation of the usability of
the U‑space services. Considering adding or removing optional services: |
|||
EASA U-space regulations require authorities to coordinate stakeholder involvement across planning, execution, and review phases. This coordination ensures safe drone operations through designation, airspace restrictions, and service determination. Consultation, monitoring, and evaluation are key to adapting U-space to evolving needs and integrating feedback for continuous improvement.