ED Decision 2023/014/R
CONTENT OF THE PRODUCTION ORGANISATION EXPOSITION
(a) All staff should be familiar with those production organisation exposition (POE) parts that are relevant to their tasks.
(b) A paragraph in the POE should provide a description of the organisation, as well as the safety policy and the corresponding objectives, as required by point 21.A.139(c)(1).
(c) The POE should include a statement, signed by the accountable manager (and countersigned by the senior company manager, if different), which confirms that the POE and any associated manuals are complied with at all times.
This statement should read as follows, or embrace the intent of the following text:
âThis exposition defines the organisation and the procedures upon which the competent authorityâs* production organisation approval (POA) is based.
These procedures are approved by the undersigned, and must be complied with, as applicable, to ensure that all production activities are performed on time and to an approved standard.
It is understood that the approval of the production organisation (PO) is based on the organisationâs continuous compliance with the applicable requirements of Part 21, and with the organisationâs procedures that are described in this exposition. The competent authority* is entitled to limit, suspend, or revoke the approval if the organisation fails to fulfil the obligations that are imposed by Part 21, or any conditions according to which the approval was issued.
Signed ......................................
Dated ......................................
Accountable manager and ...................................... (quote the position of the signatory)
Senior company manager ......................................
For and on behalf of ...................................... (quote the organisationâs name)â
*Where âcompetent authorityâ is stated, please insert the actual name of the approving competent-authority organisation or administration that grants the POA.
The statement should be reissued at the earliest opportunity when the accountable manager changes.
(d) The POE should include the description of the internal safety reporting scheme that is required by point 21.A.3A(b)(1).
(e) The POE should include the safety management procedures (including identification of safety hazards, evaluation, and associated risks management), safety assurance procedures, and safety promotion processes.
(f) If the organisation holds one or more additional organisation certificates within the scope of Regulation (EU)Â 2018/1139 and the delegated and implementing acts that are adopted on the basis thereof, so that the organisation is required to establish another exposition, the organisation may combine the documents by producing a separate manual or supplement that covers the differences between the POE and the other exposition. In that case, the manual or supplement should identify where in the other exposition the remaining information on the production organisation (PO) is covered. That remaining information then formally becomes part of the exposition.
(g) The organisation may document its safety policy, safety objectives, and all the safety management system key processes (as required by point 21.A.139(c)) in a separate manual (e.g. a safety management manual or management system manual) or in its POE. Organisations that hold multiple organisation approvals, which are issued under Regulation (EU) 2018/1139 and the delegated and implementing acts that are adopted on the basis thereof, may prefer to have a separate manual to avoid duplication.
AMC1 21.A.143(a)(1) details POE content: staff familiarity, safety policy, signed compliance statement, internal reporting, safety management procedures, and options for combining expositions or separate manuals.