ED Decision 2021/009/R
M.A. SUBPART G APPROVAL RECOMMENDATION REPORT EASA FORM 13 |
|
Part 1: General
Name of organisation:
Approval reference:
Requested approval rating/
EASA Form 14 or AOC dated*:
Other approvals held (if app.)
Address of facility(ies) audited: |
|
Audit period: from |
to |
Date(s) of audit(s):
Audit reference(s):
Persons interviewed:
|
|
Competent authority surveyor:
Competent authority office: |
Signature(s):
Date of EASA Form 13 Part 1 completion: |
*delete as appropriate |
|
M.A. SUBPART G APPROVAL RECOMMENDATION REPORT EASA FORM 13 |
|||||||||||||
Part 2: M.A. Subpart G Compliance Audit Review |
|||||||||||||
The five columns may be labelled and used as necessary to record the approval product line or facility, including subcontractor’s, reviewed. Against each column used of the following M.A. Subpart G subparagraphs, please either tick (Ö) the box if satisfied with compliance, or cross (X) the box if not satisfied with compliance and specify the reference of the Part 4 finding next to the box, or enter N/A where an item is not applicable, or N/R when applicable but not reviewed. |
|||||||||||||
Para |
Subject |
|
|
|
|
|
|||||||
|
|||||||||||||
Extent of approval |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Continuing airworthiness |
|
|
|
|
|
|
|
|
|
|
|
||
management exposition (see Part 3) |
|
|
|
|
|
|
|
|
|
|
|||
|
|||||||||||||
Facilities |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Personnel requirements |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Airworthiness review staff |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Continuing airworthiness |
|
|
|
|
|
|
|
|
|
|
|
||
management |
|
|
|
|
|
|
|
|
|
|
|||
|
|||||||||||||
|
|||||||||||||
Occurrence reporting |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Documentation |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Airworthiness review |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Privileges of the organisation |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Quality system |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Changes to the approved continuing |
|
|
|
|
|
|
|
|
|
|
|
||
airworthiness organisation |
|
|
|
|
|
|
|
|
|
|
|||
|
|||||||||||||
Record-keeping |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
Findings |
|
|
|
|
|
|
|
|
|
|
|
||
|
|||||||||||||
|
|||||||||||||
Competent authority surveyor(s): |
|
Signature(s): |
|
||||||||||
|
|
|
|
||||||||||
|
|
|
|||||||||||
Competent authority office: |
Date of EASA Form 13 Part 2 completion: |
||||||||||||
|
|||||||||||||
M.A. SUBPART G APPROVAL RECOMMENDATION REPORT EASA FORM 13 |
||
Part 3: Compliance with M.A. Subpart G continuing airworthiness management exposition (CAME) Please either tick (Ö) the box if satisfied with compliance; or cross (x) if not satisfied with compliance and specify the reference of the Part 4 finding; or enter N/A where an item is not applicable; or N/R when applicable but not reviewed. |
||
PART 0 |
General organisation |
|
0.1 |
|
Corporate commitment by the accountable manager |
0.2 |
|
General information |
0.3 |
|
Management personnel |
0.4 |
|
Management organisation chart |
0.5 |
|
Notification procedure to the competent authority regarding changes to the organisation’s activities/approval/location/personnel |
0.6 |
|
Exposition amendment procedures |
PART 1 |
Continuing airworthiness management procedures |
|
1.1 |
|
Aircraft technical log utilisation and MEL application Aircraft continuing airworthiness record system utilisation |
1.2 |
|
Aircraft maintenance programmes – development amendment and approval |
1.3 |
|
Time and continuing airworthiness records, responsibilities, retention, access |
1.4 |
|
Accomplishment and control of airworthiness directives |
1.5 |
|
Analysis of the effectiveness of the maintenance programme(s) |
1.6 |
|
Non mandatory modification embodiment policy |
1.7 |
|
Major repair and modification standards |
1.8 |
|
Defect reports |
1.9 |
|
Engineering activity |
1.10 |
|
Reliability programmes |
1.11 |
|
Pre-flight inspections |
1.12 |
|
Aircraft weighing |
1.13 |
|
Check flight procedures |
PART 2 |
Quality system |
|
2.1 |
|
Continuing airworthiness quality policy, plan and audits procedure |
2.2 |
|
Monitoring of continuing airworthiness management activities |
2.3 |
|
Monitoring of the effectiveness of the maintenance programme(s) |
2.4 |
|
Monitoring that all maintenance is carried out by an appropriate maintenance organisation |
2.5 |
|
Monitoring that all contracted maintenance is carried out in accordance with the contract, including subcontractors used by the maintenance contractor |
2.6 |
|
Quality audit personnel |
PART 3 |
Contracted Maintenance |
|
3.1 |
|
Procedures for contracted maintenance |
3.2 |
|
Quality audit of aircraft |
PART 4 |
Airworthiness review procedures |
|
4.1 |
|
Airworthiness review staff |
4.2 |
|
Review of aircraft records |
4.3 |
|
Physical survey |
4.4 |
|
Additional procedures for recommendations to competent authorities for the import of aircraft |
4.5 |
|
Recommendations to competent authorities for the issue of airworthiness review certificates |
4.6 |
|
Issuance of airworthiness review certificates |
4.7 |
|
Airworthiness review records, responsibilities, retention and access |
PART 4B |
Permit to fly procedures |
|
4B.1 |
|
Conformity with approved flight conditions |
4B.2 |
|
Issue of permit to fly under the CAMO privilege |
4B.3 |
|
Permit to fly authorised signatories |
4B.4 |
|
Interface with the local authority for the flight |
4B.5 |
|
Permit to fly records, responsibilities, retention and access |
PART 5 |
Appendices |
|
5.1 |
|
Sample Documents |
5.2 |
|
List of airworthiness review staff |
5.3 |
|
List of subcontractors as per M.A.711(a)(3) |
5.4 |
|
List of approved maintenance organisations contracted |
5.5 |
|
Copy of contracts for subcontracted work (Appendix II to AMC M.A.711(a)(3)) |
CAME Reference: CAME Amendment: Competent authority audit staff: Signature(s):
Competent authority office: Date of EASA Form 13 Part 3 completion: |
||
M.A. SUBPART G APPROVAL RECOMMENDATION REPORT EASA FORM 13 |
|||||
Part 4: Findings regarding M.A. Subpart G compliance status Each level 1 and 2 finding should be recorded whether it has been rectified or not and should be identified by a simple cross reference to the Part 2 requirement. All non-rectified findings should be copied in writing to the organisation for the necessary corrective action. |
|||||
Part 2 or 3 ref. |
Audit reference(s): Findings |
L e v e l |
Corrective action |
||
Date Due |
Date Closed |
Reference |
|||
|
|
|
|
|
|
M.A. SUBPART G APPROVAL RECOMMENDATION REPORT EASA FORM 13 |
Part 5: M.A. Subpart G approval or continued approval or change recommendation* |
Name of organisation:
Approval reference:
Audit reference(s):
The following M.A. Subpart G scope of approval is recommended for this organisation:
Or, it is recommended that the M.A. Subpart G scope of approval specified in EASA Form 14 referenced ...................................................... be continued.
Name of recommending competent authority surveyor:
Signature of recommending competent authority surveyor:
Competent authority office:
Date of recommendation:
EASA Form 13 review (quality check): Date:
*delete as appropriate |
EASA Form 13 is the M.A. Subpart G approval recommendation report, structured in five parts covering general info, compliance audit, CAME review, findings, and recommendation.
* Summary by Aviation.Bot - Always consult the original document for the most accurate information.
Loading collections...