ED Decision 2020/002/R
EXTENSION OF THE OVERSIGHT PLANNING CYCLE BEYOND 24 MONTHS
(a) If the competent authority applies an oversight planning cycle that exceeds 24 months, it should, at a minimum, perform one focused inspection of the organisation (inspection of a specific area, element or aspect of the organisation) within each 12-month segment of the cycle to support the extended oversight programme.
NOTE: Where another inspection can be linked to the oversight of the organisation (e.g. when an aircraft managed by the organisation is inspected through ACAM survey), then the competent authority may take credit of such inspection to maintain the extension beyond 24 months.
(b) If the results of this inspection indicate a decrease in the safety performance or regulatory compliance of the organisation, the competent authority should revert to a 24-month (or less) oversight planning cycle and review the oversight programme accordingly.
(c) In order to be able to approve an oversight planning cycle of beyond 36 months, the competent authority should agree on the format and contents of the continuous reporting to be made by the organisation on its safety performance and regulatory compliance.
Loading collections...