AMC1 145.B.305(c) Oversight programme

ED Decision 2022/011/R

OVERSIGHT PLANNING CYCLE — AUDIT AND INSPECTION

(a) When determining the oversight planning cycle and defining the oversight programme, the competent authority should assess the risks related to the activity and set-up of each organisation, and adapt the oversight to the level of risk identified and to the effectiveness of the organisation’s management system, in particular its ability to effectively manage safety risks.

(b) The competent authority should establish a schedule of audits and inspections that is appropriate to each organisation. The planning of audits and inspections should take into account the results of the hazard identification and the risk assessment conducted and maintained by the organisation as part of the organisation’s management system. Inspectors should work in accordance with the schedule provided to them.

(c) When the competent authority, having regard to the level of risk identified and the effectiveness of the organisation’s management system, varies the frequency of an audit or inspection, it should ensure that all aspects of the organisation’s activity are audited and inspected within the applicable oversight planning cycle.