ED Decision 2022/011/R
ACCOUNTABLE MANAGER STATEMENT
Part 1 of the MOE should include a statement signed by the accountable manager (and countersigned by the chief executive officer, if different), confirming that the MOE and any associated manuals will be complied with at all times.
The accountable manager’s exposition statement as specified under point 145.A.70(a)(1) should embrace the intent of the following paragraph, and in fact, this statement may be used without amendment. Any modification to the statement should not alter the intent.
‘This exposition and any associated referenced manuals define the organisation and procedures upon which the Part-145 approval certificate is issued by (competent authority*).
These procedures are endorsed by the undersigned and must be complied with, as applicable, when contracts or work orders are being progressed under the organisation approval certificate.
These procedures do not override the necessity of complying with any new or amended regulation published from time to time where these new or amended regulations are in conflict with these procedures.
It is understood that the approval of the organisation is based on the continuous compliance of the organisation with Part-145, Part-M and Part-ML, as applicable, and with the organisation’s procedures described in this exposition. The competent authority* is entitled to limit, suspend, or revoke the approval certificate if the organisation fails to fulfil the obligations imposed by Part-145, Part-M and Part-ML, as applicable, or any conditions according to which the approval was issued.
Signed ........................................
Dated ..........................................
Accountable Manager and...... (quote position)........................
Chief Executive Officer …
For and on behalf of........ (quote organisation’s name)..................................................’
Note: Where it states (‘competent authority*’), please insert the actual name of the competent authority, for example, EASA, the LBA, the DGAC, etc.
Whenever the accountable manager changes, it is important that the new accountable manager signs the statement at the earliest opportunity.
AMC1 145.A.70(a)(1) specifies the accountable manager's statement for the MOE, requiring signature, countersignature, and compliance with Part-145, Part-M, and Part-ML.