ED Decision 2015/029/R
1. When training or examination is carried out under the sub-contract control system it means that for the duration of such training or examination, the Part-147 approval has been temporarily extended to include the sub-contractor. It therefore follows that those parts of the sub-contractor’s facilities, personnel and procedures involved with the Part-147 approved maintenance training organisation’s students should meet requirements of Part-147 for the duration of that training or examination and it remains the Part-147 organisation’s responsibility to ensure such requirements are satisfied.
2. The maintenance training organisation approved under Part-147 is not required to have complete facilities and personnel for training that it needs to sub-contract but it should have its own expertise to determine that the sub-contractor meets the Part-147 standards. Particular attention should be given to ensuring that the training that is delivered also meets the requirements of Part-66 and the aircraft technologies are appropriate.
3. The contract between the maintenance training organisation approved under Part-147 and the sub-contractor should contain:
- a provision for the Agency and the competent authority to have right of access to the sub-contractor;
- a provision for the sub-contractor to inform the Part-147 approved maintenance training organisation of any change that may affect its Part-147 approval, before any such change takes place.
AMC 147.A.145(d) explains that sub-contracted training temporarily extends Part-147 approval to the sub-contractor, whose relevant facilities, personnel, and procedures must meet Part-147 standards. The Part-147 org must
* Summary by Aviation.Bot - Always consult the original document for the most accurate information.