MAJOR CONSTRUCTION/MAINTENANCE WORK

(a)     Before the commencement of any substantial work on the movement area, a liaison group comprising representatives from the aerodrome operator, air traffic services, apron management services, if applicable, and subcontractors’ agents should be established.

(b)     The group could meet, as often as considered necessary, to review progress, and consider the need for any change in working practices to meet operational requirements.

(c)      As far as practicable, working areas should be blocked off from the active parts of the movement area by the erection of physical barriers.

(d)     Consideration should be given to the marking and lighting of barriers.

(e)     The lights of taxiways leading into working areas should be permanently ‘off’.

(f)      Before works commence, the following should be established:

(1)     the hours of work;

(2)     the authorised routes;

(3)     the communications facilities to be used;

(4)     the permitted heights of vehicles and equipment, and the limitations to be placed on operating heights of cranes; and

(5)     any limitation to be placed on use of electrical equipment which might cause interference with navigational facilities or aircraft communications.

(g)     Contractors should be briefed for possible hazards to personnel working on aerodromes, in particular the jet blast problem and noise.

(h)     Where contractors work on or traverse aircraft pavement areas, these areas should be inspected thoroughly before they are opened again for aircraft use, with particular attention to the presence of debris and the general cleanliness of the surface.

(i)      Where aircraft are constantly using areas open to contractors, inspections at frequent intervals are required to ensure the continuing operational safety of the aerodrome.

(j)      Adequate marking arrangements should be provided for crane jibs when extra conspicuity is considered desirable.

(k)     If work is of prolonged duration, a constant watch is required to ensure that the marking and lighting of obstacles and unserviceable areas does not degrade below acceptable limits.

(l)      The effect of tall cranes on ILS and radar, in conjunction with those responsible for electronic landing aids and steps taken to reduce limitations to the minimum, should be considered.