AMC2 ADR.AR.C.010(b);(c) Oversight programme

ED Decision 2020/021/R

OVERSIGHT PLANNING CYCLE

(a)     For each aerodrome operator and for each organisation responsible for the provision of AMS all processes should be audited at periods not exceeding the applicable oversight planning cycle. The beginning of the first oversight planning cycle is normally determined by the date of issue of the first certificate or acknowledgement of receipt of the declaration. If the Competent Authority wishes to align the oversight planning cycle with the calendar year, it should shorten the first oversight planning cycle accordingly.

(b)     The interval between two audits for a particular process should not exceed the interval of the applicable oversight planning cycle.

(c)      Audits should include at least one on-site audit within each oversight planning cycle at each aerodrome.