AMC1 ADR.OPS.C.011 Overload operations
ED Decision
2024/004/R
CRITERIA FOR OVERLOAD
OPERATIONS
(a) For those operations in which the magnitude of overload and/or
the frequency of use do not justify a detailed analysis, the aerodrome
operator should use the following criteria, in order not to adversely affect
the pavement:
(1) for flexible pavements, occasional movements by aircraft with
ACN not exceeding 10 % above the reported PCN should not adversely affect the
pavement;
(2) for rigid or composite pavements, in which a rigid pavement
layer provides a primary element of the structure, occasional movements by
aircraft with ACN not exceeding 5 % above the reported PCN should not
adversely affect the pavement;
(3) if the pavement structure is unknown, the 5 % limitation should
apply; and
(4) the annual number of overload movements should not exceed
approximately 5 % of the total annual aircraft movements.
(b) The aerodrome operator should not permit overload operations on
pavements exhibiting signs of distress or failure. Furthermore, overload
operations should be avoided during any periods of thaw following frost
penetration, or when the strength of the pavement or its subgrade could be
weakened by water. Where overload operations are conducted, the aerodrome
operator should review the relevant pavement condition regularly, and should
review the criteria for overload operations periodically, since repetition of
overloads can cause severe shortening of pavement life or require major
rehabilitation of pavement.
Aerodrome operators can allow occasional aircraft overloads (ACN exceeding PCN) on pavements, but with limitations. Flexible pavements allow 10% overload, rigid/unknown pavements 5%. Overload movements should be limited to 5% of annual traffic. Overloads are prohibited on distressed pavements or during thaw periods. Regular pavement condition reviews are essential.