AMC1 ADR.OPS.B.100(b)(5)Suspension of runway operations and runway
closure
ED Decision 2024/004/R
ACTIONS BEFORE
RECOMMENCEMENT OF RUNWAY OPERATIONS
The following actions should be
completed if runway operations are recommenced following a suspension or
closure of runway operations:
(a) remedial works are completed, e.g. clearance of FOD, wildlife
remains, runway lighting repair, removal of disabled aircraft;
(b) all vehicles and personnel have vacated the runway and report
to the air traffic services;
(c) a runway inspection under the authorisation of air traffic
services is conducted;
(d) runway availability is confirmed to air traffic services;
(e) relevant NOTAM, if published, is cancelled;
(f) runway availability is promulgated by air traffic services
using ATIS and radiotelephony.