Navigate / EASA

AMC2 ATS.OR.205(b)(4) Safety assessment and assurance of changes to the functional system

ED Decision 2020/008/R

RISK MITIGATION

When the risk evaluation results show that the safety criteria cannot be satisfied, then the air traffic services provider should either abandon the change or propose additional means of mitigating the risk. If risk mitigation is proposed, then the air traffic services provider should ensure that it identifies:

(a)     all of the elements of the functional system, e.g. training, procedures that need to be reconsidered; and

(b)     for each part of the amended change, those parts of the safety assessment (requirements from (1) to (6) listed in ATS.OR.205(b)) that need to be repeated in order to demonstrate that the safety criteria will be satisfied.