AMC1 NCC.OP.235(a)(2) EFVS 200 operations

EASA Logo
AMC1 NCC.OP.235(a)(2) EFVS 200 operations

ED Decision 2022/012/R

AERODROMES AND INSTRUMENT PROCEDURES SUITABLE FOR EFVS 200 OPERATIONS

(a) For EFVS 200 operations, the operator should verify the suitability of a runway before authorising EFVS operations to that runway through an operational assessment taking into account the following elements:

(1) the obstacle situation;

(2) the type of aerodrome lighting;

(3) the available IAPs;

(4) the aerodrome operating minima; and

(5) any non-standard conditions that may affect the operations.

(b) EFVS 200 operations should only be conducted as 3D operations, using an IAP in which the final approach track is offset by a maximum of 3 degrees from the extended centre line of the runway.

(c) The IAP should be designed in accordance with PANS-OPS, Volume I (ICAO Doc 8168) or equivalent criteria.

Frequently Asked Questions

The operator should verify the suitability of the runway before authorising EFVS operations to that runway through an operational assessment.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The operator should take into account the obstacle situation, the type of aerodrome lighting, the available IAPs, the aerodrome operating minima, and any non-standard conditions that may affect the operations.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The final approach track should be offset by a maximum of 3 degrees from the extended centre line of the runway.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

EFVS 200 operations should only be conducted as 3D operations, using an IAP in which the final approach track is offset by a maximum of 3 degrees from the extended centre line of the runway.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The IAP should be designed in accordance with PANS-OPS, Volume I (ICAO Doc 8168) or equivalent criteria.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

Runway surface condition is not listed as an element; the listed elements are the obstacle situation, the type of aerodrome lighting, the available IAPs, the aerodrome operating minima, and any non-standard conditions that may affect the operations.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

No, the section does not specify any applicability date.