AviationBot
Navigate / EASA / CS E AMDT 5 / SUBPART E - TURBINE ENGINES: TYPE SUBSTANTIATION / CS-E 740 Endurance Tests /

AMC E 740(c)(3) Endurance tests

EASA engine endurance tests (CS-E 740(c)(3)) offer two acceptable procedures: either a 150-hour test followed by inspection and a 2-hour test, or a combined 152-hour test. Brief engine speed overshoots during the 30-second OEI power test are permissible if validated. Interrupted test sequences require repetition or justified restarts maintaining thermal conditions.

Frequently Asked Questions

The Engine is reassembled using the same parts used for the 150-hour endurance test except as otherwise allowed by CS-E 740(h)(2)(ii).

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

Yes, a short overshoot of speed is acceptable if it's validated throughout the CS-E 740(c)(3)(iii) test, ensuring the shortest time of establishment of the corresponding power.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The interrupted sequence needs to be repeated in full, or can be re-started from the interrupt point if there is a technical justification acceptable to the Agency. The test should be restarted from a point where the Engine thermal condition would be the same as at the time of interruption.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The strip inspection standards applied after completion of the additional 2-hour endurance test will be those prescribed in CS-E 740(h)(2).

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

Two procedures are acceptable: (a) A 150-hour test followed by strip inspection, reassembly, and a 2-hour test, or (b) A 150-hour test immediately followed by the 2-hour test without engine disassembly.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

EASA Logo

AMC E 740(c)(3)  Endurance tests

ED Decision 2007/015/R

(1)     Two procedures for running the tests required under CS-E 740(c)(3) are acceptable:

(a)      After the basic 150-hour endurance test the Engine may be subject to a strip inspection in accordance with CS-E 740(h)(1).

The Engine is then reassembled using the same parts used for the 150-hour endurance test except as otherwise allowed by CS-E 740(h)(2)(ii) and the additional 2-hour endurance test is run to CS-E 740(c)(3)(iii).

Completion of the additional 2-hour endurance test would be followed by compliance with the strip inspection specifications of CS-E 740(h)(2)(iii); or

(b)     The 2-hour additional endurance test of CS-E 740(c)(3)(iii) may be run immediately after the basic 150-hour endurance test without Engine disassembly.

The strip inspection standards that will be applied after completion of the additional 2-hour endurance test will be those prescribed in CS-E 740(h)(2).

(2)     Per CS-E 50(f), the Engine control should prevent exceedence of the speed limitation associated with the 30-Second OEI Power rating. Nevertheless, for ensuring the shortest time of establishment of the corresponding power, it might be necessary to design the Engine control in such a manner that a short overshoot of the speed will occur at the beginning of the 30 seconds period. This is acceptable if this is validated throughout the CS-E 740(c)(3)(iii) test.

(3)     In the event of a stop occurring during the four test sequences of CS-E 740(c)(3)(iii), the interrupted sequence needs to be repeated in full or can be re-started from the interrupt point if there is a technical justification acceptable to the Agency. If it is determined that the sequence need not be repeated in its entirety, the test should be restarted from a point where the Engine thermal condition would be the same as at the time of interruption. (See CS-E 740(b)(1)).

[Amdt. No.: E/1]