CS 26.331 Compliance plan for STC holders

EASA Logo

CS 26.331 Compliance plan for STC holders

ED Decision 2020/023/R

Compliance with point 26.331 of Part-26 is demonstrated when a compliance plan exists that includes:

(a) a project schedule identifying all the major milestones for meeting the compliance times specified in points 26.332 to 26.334 of Part-26;

(b) an explanation of how the changes that affect the FCS will be identified and presented;

(c) a proposed means of compliance with the DTE required by points 26.333 and 26.334 of Part-26;

(d) a plan for submitting drafts of all the compliance items required by point 26.330 of Part-26 for review by EASA not less than 60 days before the applicable compliance date.

[Issue: 26/3]

Frequently Asked Questions

The compliance plan must include a project schedule identifying all the major milestones for meeting the compliance times specified in points 26.332 to 26.334 of Part-26.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include an explanation of how the changes that affect the FCS will be identified and presented.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include a proposed means of compliance with the DTE (damage tolerance evaluation) required by points 26.333 and 26.334 of Part-26.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include a plan for submitting drafts of all compliance items required by point 26.330 of Part-26 for review by EASA not less than 60 days before the applicable compliance date.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

CS 26.331 is associated with ED Decision 2020/023/R and is marked as Issue 26/3.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The project schedule is intended to identify all the major milestones for meeting the compliance times specified in points 26.332 to 26.334 of Part-26.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

Yes, the compliance plan must include an explanation of how changes that affect the FCS will be identified and presented.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

CS 26.331 references points 26.333 and 26.334 of Part-26 for the DTE (damage tolerance evaluation) means of compliance.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation