CS 26.301 Compliance plan for (R)TC holders and applicants

CS 26.301 mandates a compliance plan for (R)TC holders, covering project schedule, means of compliance for DTE, WFD, LOV, CPCP, and EASA submission at least 60 days before compliance dates.

Frequently Asked Questions

A compliance plan must include a project schedule identifying major milestones for meeting compliance dates, a proposed means of compliance with applicable requirements (including methods for DTE, WFD evaluation, LOV establishment, CPCP development, and more), and a plan for submitting draft compliance items to EASA at least 60 days before the applicable compliance date.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The required elements are: (a) a project schedule with major milestones for compliance dates; (b) a proposed means of compliance covering DTE, structural configuration identification, WFD-susceptible structure identification, engineering data sources, WFD evaluation, LOV establishment and distribution, maintenance actions, CPCP development, continuing structural integrity programme validity, FCBS list, and REGs development; and (c) a plan for submitting draft compliance items to EASA at least 60 days before the compliance date.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The plan must include submitting a draft of all required compliance items for review by EASA not less than 60 days before the applicable compliance date.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include methods and procedures for performing the damage tolerance evaluation (DTE) of baseline structure, modified structure, and published repairs.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include methods and procedures for identifying WFD-susceptible structure.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include methods and procedures for establishing a limit of validity (LOV) and plans for distribution upon approval, including incorporation of the LOV into the airworthiness limitation section (ALS).

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The compliance plan must include establishing a process to ensure the continuing structural integrity programme remains valid.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

The project schedule must identify all major milestones for meeting the compliance dates as specified in points 26.302 to 26.309 of Part-26, as applicable.

* Aviation.Bot's Suggestion - Always consult the original regulation for confirmation

EASA Logo

CS 26.301 Compliance plan for (R)TC holders and applicants

ED Decision 2020/023/R/R

Compliance with point 26.301 of Part-26 is demonstrated when a compliance plan exists that includes the following:

(a) a project schedule identifying all the major milestones for meeting the compliance dates as specified in points 26.302 to 26.309 of Part-26, as applicable;

(b) a proposed means of compliance with the applicable requirements as specified in points 26.302 to 26.309 of Part-26, including as appropriate, methods and procedures for:

(1) performing the damage tolerance evaluation (DTE) of baseline structure, modified structure and published repairs;

(2) identifying the aeroplane structural configuration to be evaluated;

(3) identifying widespread fatigue damage (WFD)-susceptible structure;

(4) identifying the source of engineering data that will be used to perform the required evaluations;

(5) performing the WFD evaluation of structure;

(6) establishing a limit of validity (LOV) and plans for distribution upon approval (including incorporation of the LOV into the (airworthiness limitation section) ALS);

(7) identifying and developing the maintenance actions required to support the LOV;

(8) developing a baseline corrosion prevention and control programme (CPCP);

(9) establishing a process to ensure the continuing structural integrity programme remains valid;

(10) establishing the list of fatigue-critical baseline structures (FCBSs);

(11) developing the repair evaluation guidelines (REGs);

(c) a plan for submitting a draft of all the required compliance items for review by EASA not less than 60 days before the applicable compliance date.

[Issue: 26/3]